This report gives information about the project status. Whether it is On track, Off track, or At risk.
For Story points and Issue count:
If we have less than 85 - 89% issues/story points completed - At risk.
If 90 - 100% of issues/story points completed - On track.
If we have less than 85% - Off track.
For Work ratioRemeining estimate:
Off Track: If the work ratio is above a certain threshold, it indicates that the project is falling behind schedule. You might set a threshold like 120%, meaning if the work ratio exceeds 120%, the project is considered off trackremaining estimate completion is less than 85%.
On Track: If the work ratio is within an acceptable range, the project is on track. This range could be, for example, between 89% and 120%.remaining estimate completion is more than 90%.
At Risk: If the work ratio is below a certain threshold, it indicates that the project may be at risk of not meeting its targets. This threshold could be, for instance, 89%.remaining estimate completion is in the range of 85-90%.
...
While hovering the line tooltip appears. It shows the selected date (one the user is hovering over), guideline (showing the planned amount of completed values till the chosen moment), and unresolved value (amount of left values till the setting due date).
Labels on the line can be added and removed. While they are added the user can see the number of tasks created or resolved at a certain moment.
The report is built considering all issue types.
...
Setting up a report
The report has 4 tabs of configurations: Data source, Parameters, Display, Description.
...
The Version field is required. It lets the user select the tickets related to a certain version.
Note |
---|
The report is built on actual data. After adding or removing issues from the Sprint or Version it will impact the initial amount of issues and report as a whole. |
Saved filter select
...
The Saved filter field is required. It lets the user filter issues by existing filters.
...
Some specifics about duration in case of choosing Version in DataSourceData Source:
If the Version has a start and end date it will be set in Duration fields.
If the Version has a start date and the end date is absent, in duration field will be shown the start date. In that case, user has to specify the end date.
If the Version has an end date and the start date is absent, in duration field will be shown the end date. In that case, user have to specify the start date.
The Metric field is required. It lets the user choose the metric of the key performance indicator by which the report will be calculated. For example: Issue count, Story points, and Work ratio Remaining estimate.
The Include weekends toggle provides the user the possibility to include or exclude weekends while building a report.
...