  • This report gives information about the project status. Whether it is On track, Off track, or At risk.

  • For Story points and Issue count:

    • If we have less than 85 - 89% issues/story points completed - At risk.

    • If 90 - 100% of issues/story points completed - On track.

    • If we have less than 85% - Off track.

  • For Remeining estimate:

    • Off Track: If the remaining estimate completion is less than 85%.

    • On Track: If the remaining estimate completion is more than 90%.

    • At Risk: If the remaining estimate completion is in the range of 85-90%.

...

Duration field is required. There user can choose a start and end date in a datepicker. Out of this will be defined a timeframe for the report. The minimum timeframe can be 2 days, maximum - 2 months.

...

  • If there is a start date and end day set for Sprint, they will be automatically set in the duration field.

  • If a custom duration is selected, the start date and end date will be taken only if they have been specified in Sprint.In case dates haven`t been specified, the user has to select them in the Duration field.

Some specifics about duration in case of choosing Version in Data Source:

...