  • This report gives information about the project status. Whether it is On track, Off track, or At risk.

  • For Story points and Issue count:

    • If we have less than 85 - 89% issues/story points completed - At risk.

    • If 90 - 100% of issues/story points completed - On track.

    • If we have less than 85% - Off track.

  • For Remeining estimate:

    • Off Track: If the remaining estimate completion is less than 85%.

    • On Track: If the remaining estimate completion is more than 90%.

    • At Risk: If the remaining estimate completion is in the range of 85-90%.

...

The JQL field lets user filter issues by using JQL requests. The report uses Atlassian’s JQL component so it has syntax checking and auto-complete implemented. When the user finishes inserting the JQL the user needs to can validate the JQL using the button underneath the input. Number of issues is clickable. By clicking, the user is redirected to the page with a list of issues in the Jira project.

...