This report gives information about the project status. Whether it is On track, Off track, or At risk.
For Story points and Issue count:
If we have less than 85 - 89% issues/story points completed - At risk.
If 90 - 100% of issues/story points completed - On track.
If we have less than 85% - Off track.
For Remeining estimate:
Off Track: If the remaining estimate completion is less than 85%.
On Track: If the remaining estimate completion is more than 90%.
At Risk: If the remaining estimate completion is in the range of 85-90%.
...
While hovering the line tooltip appears. It shows the selected date (one the user is hovering over), guideline (showing the planned amount of completed values till the chosen moment), and unresolved value (amount of left values till the set due date).
Labels on the line can be added and removed. While they are added the user can see the number of tasks created or resolved at a certain moment.
The report is built considering all issue types.
...
Setting up a report
The report has 4 tabs of configurations: Data source, Parameters, Display, Description.
...