This report gives information about the project status. Whether it is On track, Off track, or At risk.
For Story points and Issue count:
If we have less than value in the range of 85 - 89% issues/story points completed - At risk.
If 90 - 100% of issues/story points completed - On track.
If we have less than 85% - Off track.
For Remeining estimate:
Off Track: If the remaining estimate completion is less than 85%.
On Track: If the remaining estimate completion is more than 90%.
At Risk: If the remaining estimate completion is in the range of 85-90%.
...
Duration field is required. There user can choose a start and end date in a datepicker. Out of this will be defined a timeframe for the report. The minimum timeframe can be 2 days, maximum - 2 months60 days.
Some specifics about duration in case of choosing Sprint in DataSource:
...