This report gives information about project status. Whether it is On track, Off track or At risk. (
For Story points and Issue count:
If we have less than 85 - 89% issues completed - At risk.
If 90 - 100% issues completed - On track.
If we have less than 85% - Off track
.
For Work ratio:
Off Track: If the work ratio is above a certain threshold, it indicates that the project is falling behind schedule. You might set a threshold like 120%, meaning if the work ratio exceeds 120%, the project is considered off track.
On Track: If the work ratio is within an acceptable range, the project is on track. This range could be, for example, between 89% and 120%.
At Risk: If the work ratio is below a certain threshold, it indicates that the project may be at risk of not meeting its targets. This threshold could be, for instance, 89%.
...
While hovering the line tooltip appears. It shows the selected date (one that user is hovering), guideline (show the planned amount of completed values till chosen moment), unresolved value (amount of left values till the setting due date).
...
Some specifics about duration in case of choosing Sprint in DataSource:
If there is a start date setted for Sprint and a duration , (except for custom,) the end day will be calculated the end day based on that if end date is emptythem.
If a custom duration is selected, will be taken start date and end date will be taken only if they have been specified in Sprint.
In case if dates haven`t been specified, user has to select them in Duration fields.
Some specifics about duration in case of choosing Version in DataSource:
...