  • This report gives information about the project status. Whether it is On track, Off track, or At risk.

  • For Story points and Issue count:

    • If we have less than 85 - 89% issues completed - At risk.

    • If 90 - 100% of issues completed - On track.

    • If we have less than 85% - Off track.

  • For Work ratio:

    • Off Track: If the work ratio is above a certain threshold, it indicates that the project is falling behind schedule. You might set a threshold like 120%, meaning if the work ratio exceeds 120%, the project is considered off track.

    • On Track: If the work ratio is within an acceptable range, the project is on track. This range could be, for example, between 89% and 120%.

    • At Risk: If the work ratio is below a certain threshold, it indicates that the project may be at risk of not meeting its targets. This threshold could be, for instance, 89%.

...

  • While hovering the line tooltip appears. It shows the selected date (one the user is hovering over), guideline (showing the planned amount of completed values till the chosen moment), and unresolved value (amount of left values till the setting due date).

...

"Duration“ fields are required. There user can choose a start and end date in a datepicker. Out of this will be defined duration. Datepicker also contains a dateswapper, allowing the user to quickly switch monthsa timeframe. The minimum timeframe can be 2 days, maximum - 3 months.

...

  • If there is a start date set for Sprint and a duration (except for custom)  the , the end day will be calculated based on them.

  • If a custom duration is selected, the start date and end date will be taken only if they have been specified in Sprint.

  • In case dates haven`t been specified, the user has to select them in the Duration fields.

...